Key Points

A connected kitchen, pantry, and laundry room can be remodeled as one project, but it'll take longer than 7 days because it isn't just a kitchen.
Traditional remodels stall during the installation when all decisions haven’t been made, materials aren’t on-site, and trades aren’t locked in, which is why all three get settled during our 4 to 6 week planning phase.
A dialed-in planning process is what holds the schedule, whether that is 7 days for a kitchen or 10 to 14 for a multi-room project.

Four Kids, Three Rooms, and a Kitchen That Finally Keeps Up

Can the kitchen, the pantry, and the laundry room all get done at the same time?

Or do you fix the kitchen now and come back for the other two in a few years?

In this post, you’ll learn what a combined kitchen, pantry, and laundry remodel involves, how 7 Day Kitchens planned three connected rooms in Charlotte as one project, and why multi-room projects usually drag when they aren’t planned our way.

Can You Remodel a Kitchen, Pantry, and Laundry in One Project?

Yes, a kitchen, pantry, and laundry room can be remodeled as one project, and connected rooms are usually better handled that way.

The three spaces often share plumbing lines, electrical circuits, flooring, and the same morning traffic.

Handled together, they get one design, one materials order, and one team.

We call these Kitchen+ projects.

They cover pantries, sculleries, laundry rooms, closets, coffee bars, drop zones, and structural changes like taking out a wall.

There is one main rule with these projects: Kitchen+ is only available when we are also doing your kitchen.

Since it’s no longer just a kitchen project, the timeline can extend beyond 7 days, depending on the scope.

Some Kitchen+ projects can fit inside that same timeframe, but bigger multi-room projects usually run 10 to 14 days. This is because every added room brings its own cabinetry, its own trades, and sometimes its own plumbing.

Inside a Charlotte, NC Kitchen, Pantry, and Laundry Remodel

Catherine and Tyler had four kids and a kitchen that could not keep up with any of them.

Mornings were the worst.

  • There was never enough room for everyone to be in the kitchen at once.
  • Poor storage meant cluttered countertops, removing space needed to set up taco night.
  • The pantry and the laundry room sat next to all of it as disorganized afterthoughts that made everything more complicated.

We rebuilt the kitchen, the pantry, and the laundry room in the same project, for an investment of $119,000.

Start to finish, it ran 10 days. The kitchen installation took 7 of them, and refinishing the hardwood took the other 3.

Now their mornings work.

Cooking is fun again, and taco night is no longer a logistical problem.

The same design runs through the kitchen, the pantry, and the laundry, so all three rooms support how this family actually moves through the day.

“I had a vision and had talked to Barry and Michelle about it. When I saw it in person, it was better than I could have imagined. Now we’re excited to show it off.”

– Tyler and Catherine, Charlotte, NC

How Three Connected Spaces Were Planned as One

It started at the in-home discovery meeting, where we documented how a family with four kids actually used the kitchen. 

Michelle McHenry, our interior designer, led it. 

Michael, our architectural designer, came with her.

Michelle came with the samples and walked Catherine and Tyler through cabinets, countertops, backsplash, hardware, and lighting, weighing in when they could not decide. 

This meeting is where the Calacatta Laza Oro quartz and the brushed gold hardware got chosen, and where the Truemade Shaker cabinetry got carried into the pantry and the laundry instead of stopping at the kitchen door.

Michael took the site measurements that day, plus photos and video of the rooms as they stood.

He turned those numbers into the drawings, working them out with Catherine, Tyler, and Michelle. 

They saw floor plans and elevations placing every cabinet, appliance, and fixture, and 3D renderings of the cabinetry running out of the kitchen, through the pantry, and into the laundry.

This planning phase usually runs 4 to 6 weeks.

How One Team Kept All Three Rooms Moving Together

Our installation week runs on a sequence set in advance, where each trade enters and exits at the exact point the work calls for it.

Carpenters, electricians, plumbers, drywall, paint, and tile are all trade partners who work only inside our system, are trained on our standards and our jobsite practices, and they are the same people from start to finish.

No trade is waiting on another.

No step is performed out of order.

Jason Castelano, our project manager, is on site every day. He walks the work as it happens and clears punch-list items the day they turn up rather than three weeks later.

With the pantry and the laundry in the same scope, that sequence covers the plumbing and venting rework behind the stacked washer and dryer, the cabinetry in all three rooms, and the hardwood running through every one of them.

Why Multi-Room Projects Usually Bog Down, and How This One Did Not

There are three main reasons a traditional kitchen installation stalls:

  1. All decisions haven’t been made.
  2. Materials aren’t on-site.
  3. A trade isn’t ready.

Every one of them happens after the demo is done, meaning your kitchen is going to be torn apart for longer.

This is how we prevent all 3 of those from happening:

  1. You approve all the selections based on the floor plans, elevations, and 3D rendering.
  2. All materials are on-site and pass inspection before we schedule the installation week.
  3. We use trades that work within our system, and their time slots are locked in before the installation.

Kitchen remodeling mistakes and how we avoid them.

What a Homeowner Planning a Larger Project Can Take Away

You can remodel a kitchen, pantry, and laundry room together, and the installation doesn’t have to take months.

With 7 Day Kitchens, you only have to be without your space for days, so you could take a family vacation and come back to a new home!

Our detailed planning is why our clients are always happy with how their new space works and looks.

If It Touches Your Kitchen Remodel, 7 Day Kitchens Can Handle It, Too

Pantries, laundry rooms, bathrooms, closets, and coffee bars can all be part of the same project, on the same schedule, as long as the kitchen is part of it.

Fill out our contact form or give us a call today, and tell us what other rooms you want remodeled along with your kitchen.

Frequently Asked Questions

Can I add the pantry and laundry room after the design phase has started?

Yes, you can add rooms any time before your plans are finalized, and we are happy to look at other areas of the home. Expect it to extend the planning and design phase, since the new space has to be designed and materials need to be ordered and staged alongside the kitchen. Once selections and plans are complete, a late addition usually becomes its own separate project.

Are the pantry and laundry room covered by the same warranty as the kitchen?

Every Kitchen+ space carries the same Lifetime Workmanship Warranty and concierge care as your kitchen. Cabinets, countertops, fixtures, and appliances also carry their manufacturer warranties, which we register and document for you.

Does new flooring stop at the kitchen, or can it continue into the pantry and laundry?

If you want that same flooring to continue through adjacent rooms or your whole main level, we include it in your proposal and plan around it.